Media Summary: Crews place roller-compacted concrete (RCC) on the southern half of the Lake Crews continue to place roller-compacted concrete (RCC) on the southern half of the emergency A time-lapse view of construction at Lake

Oroville Spillways Phase 2 Update August 1 2018 - Detailed Analysis & Overview

Crews place roller-compacted concrete (RCC) on the southern half of the Lake Crews continue to place roller-compacted concrete (RCC) on the southern half of the emergency A time-lapse view of construction at Lake Work continues through the night and into the morning hours on the Material is processed at the rock crushing plant before being transported to the roller-compacted concrete (RCC) plant for the ... Crews clean the rock foundation of the Lake

Crews lay roller-compacted concrete (RCC) for the emergency Mechanical demolition continues at the energy dissipator blocks at the bottom of the main Crews place final leveling concrete on the upper chute of the main Crews place structural concrete for two walls in the middle chute of the main Crews hydroblast concrete on the dentates of the main Crews continue to place leveling concrete on the upper chute of the Lake

Photo Gallery

Oroville Spillways Phase 2 Update August 1, 2018
Oroville Spillways Phase 2 Update August 15, 2018
Oroville Spillways Phase 2 Update August 17, 2018
Oroville Spillways Phase 2 Update August 31, 2018
Oroville Spillways Phase 2 Update August 29, 2018
Oroville Spillways Phase 2 Update August 24, 2018
Oroville Spillways Phase 2 Update August 14, 2018
Oroville Spillways Phase 2 Update Mid-June 2018
Oroville Spillways Phase 2 Update June 20, 2018
Oroville Spillways Phase 2 Update August 8, 2018
Oroville Spillways Phase 2 Update August 22, 2018
Oroville Spillways Phase 2 Update Mid-April 2018
Sponsored
Sponsored
View Detailed Profile
Oroville Spillways Phase 2 Update August 1, 2018

Oroville Spillways Phase 2 Update August 1, 2018

Crews place roller-compacted concrete (RCC) on the southern half of the Lake

Oroville Spillways Phase 2 Update August 15, 2018

Oroville Spillways Phase 2 Update August 15, 2018

Crews continue to place roller-compacted concrete (RCC) on the southern half of the emergency

Sponsored
Oroville Spillways Phase 2 Update August 17, 2018

Oroville Spillways Phase 2 Update August 17, 2018

A time-lapse view of construction at Lake

Oroville Spillways Phase 2 Update August 31, 2018

Oroville Spillways Phase 2 Update August 31, 2018

Work continues through the night and into the morning hours on the

Oroville Spillways Phase 2 Update August 29, 2018

Oroville Spillways Phase 2 Update August 29, 2018

Material is processed at the rock crushing plant before being transported to the roller-compacted concrete (RCC) plant for the ...

Sponsored
Oroville Spillways Phase 2 Update August 24, 2018

Oroville Spillways Phase 2 Update August 24, 2018

Crews clean the rock foundation of the Lake

Oroville Spillways Phase 2 Update August 14, 2018

Oroville Spillways Phase 2 Update August 14, 2018

From July 31 through

Oroville Spillways Phase 2 Update Mid-June 2018

Oroville Spillways Phase 2 Update Mid-June 2018

Crews lay roller-compacted concrete (RCC) for the emergency

Oroville Spillways Phase 2 Update June 20, 2018

Oroville Spillways Phase 2 Update June 20, 2018

Mechanical demolition continues at the energy dissipator blocks at the bottom of the main

Oroville Spillways Phase 2 Update August 8, 2018

Oroville Spillways Phase 2 Update August 8, 2018

Crews place final leveling concrete on the upper chute of the main

Oroville Spillways Phase 2 Update August 22, 2018

Oroville Spillways Phase 2 Update August 22, 2018

Crews place structural concrete for two walls in the middle chute of the main

Oroville Spillways Phase 2 Update Mid-April 2018

Oroville Spillways Phase 2 Update Mid-April 2018

Crews hydroblast concrete on the dentates of the main

Oroville Spillways Phase 2 Update July 12, 2018

Oroville Spillways Phase 2 Update July 12, 2018

Crews continue to place leveling concrete on the upper chute of the Lake